HSE Performance
As of 01 January 2005 = 1,710,807.4 direct PT. Heat Exchangers Indonesia man-hours, Subcontracts man-hours from 31 March 2005= 1,051,882.4 and HSE statistics are provided weekly by Safety Officers.
|
|
Statistic Incidents Period per Week
Date : 31/05/2011 No. of Fatal Accident : 0 Fatal Accident Rate : 0 No. of Accident Rate : 0 No. of Minor Injuries : 0 No. of Time Injuries : 0 Total Man-hours Lost : 0 Total Days Lost : 0 Near Miss Accident : 0 Property Demage Accident : 0 Oil Sipil : 0 First Aids case : 0 Medical Treatment Case : 0 Total Man-hours Worked : 2,762,689.8 We have worked : 2894 Days without Lost Time accident Target Every Project : 0% Incident Rate : 0
|
HSE Activities :
1. Safety Tool Box Meeting every Wednesday.
2. Check medicine stock at all first aid box every Monday.
3. Monitor employees PPE.
4. Daily check gas bottle condition.
5. Support setup & dismantle scaffolding to backup production progress to ensure all project run with safety requirement.
6. Daily monitoring of housekeeping.
7. Identification and evaluation of update all HSE hazard or aspects and the management of their risk or impact to acceptable levels.
8. Reduction of waste and conservation of resources.
9. Mapping and update fire extinguisher location.
10. Update Emergency Exit route.
11. Update Safety sign board inside workshop area.
12. Review and revised HSE manual & procedure. |
|
|
|